How Long Does Custom Software Take? Realistic Timelines by Project Type

A website, an app and an ERP follow very different schedules. See realistic ranges by project type, the phases inside them and what usually causes delays.

By the CodeElectron engineering teamUpdated 6 min read
Illustration of a project calendar with highlighted phases and a completed milestone

Key takeaways

  • Timelines depend on scope, integrations, decisions and testing, not only on coding time.
  • Typical ranges: a company website in weeks, an app or store in two to five months, a custom ERP in phases over many months.
  • Delays usually come from slow feedback, changing scope, unready content and late integrations, rather than from the code itself.
  • Plan in phases with a working release at each stage, so progress is visible and the schedule stays honest.

Why “how long” has no single answer

Asking how long software takes is like asking how long a building takes: it depends on size, design, materials and approvals. For software the biggest influences are the number of features, user roles and integrations, how quickly decisions and content arrive, and how much testing the product needs. The ranges below are planning guides for a focused team, not promises.

Typical ranges by project type

ProjectTypical planning rangeWhat stretches it
Landing page or small company siteA few weeksContent, translations, approvals
Online storeAbout two to four monthsCatalogue size, payments, shipping, stock integration
Mobile app MVPAbout two to four monthsNumber of roles, backend, store approvals
Custom web platformThree to six months for a first releaseBusiness rules, integrations, data migration
ERP or large business systemDelivered in phases over many monthsModules, migration, training, change management

The phases inside every project

  1. 1Discovery and scoping: goals, users, flows and an estimate.
  2. 2Design: structure, screens and a prototype tested with users.
  3. 3Build: development in short cycles with working demos.
  4. 4Testing: functional checks, security, performance and real devices.
  5. 5Launch: deployment, data migration and training.
  6. 6Stabilisation: fixes and quick improvements after real use.

What really causes delays

  • Slow feedback. A decision that waits a week for approval costs a week.
  • Scope that grows. Each added feature moves the date unless something leaves.
  • Content that is not ready: texts, photos, product data and translations.
  • Late integrations. Waiting for access to a payment provider or an old system stalls the work.
  • Skipped discovery, which turns later surprises into rework.

A worked example

Imagine a mobile ordering app. Discovery and prototype take two to three weeks. Building the core flow and the admin panel takes about six to eight weeks, with a demo every two weeks. Testing and store submission take another two to three weeks, and the review by the app stores can add a few days. Delays most often appear in two places: menu and price data that arrives late, and the payment provider’s approval. This is an illustrative schedule, not a promise, but it shows where to protect time.

How to keep a schedule honest

  • Release a working slice every few weeks so progress is visible.
  • Name one decision maker who can answer within a day.
  • Prepare content and accounts early, in parallel with development.
  • Hold a buffer for testing and store or provider approvals.
  • Be wary of any plan that promises a complex product in days.

Watch for early warning signs

  • Demos keep being postponed or show only mock-ups instead of working features.
  • Questions to the client pile up without answers, so work stalls.
  • Testing is left until the last week instead of running every cycle.

Next step

Use the app scope estimator to see how large your project is, learn how to start small in our MVP guide, or contact us for a phased plan.

Frequently asked questions

How long does it take to build a mobile app?

A focused first version often takes two to four months including design, development, testing and store approval. Complex apps with payments, tracking and several roles take longer.

Why do software projects run late?

Usually because of slow feedback, growing scope, content that is not ready and integrations that arrive late. Phasing the work and releasing small pieces keeps delays visible and small.

Can a project be done faster by adding more developers?

Only up to a point. More people add coordination work, and some tasks cannot be split. Clear scope and fast decisions usually save more time than extra hands.